StoryPole/Concrete

How many yards do I need

Slabs, footings, piers and stairs. Add every pour on the job, get one order and a materials list you can hand to the supply house.


Units Waste
Pour
Isometric view of the pour drawn to scale
Material ticket
0.00 cubic yards Enter your dimensions to start

    How the numbers are worked out

    Every shape resolves to cubic feet, then divides by 27 for cubic yards. Waste is applied once, to the combined total, so adding pours never compounds the allowance.

    Slab

    Length × width × thickness. A 4″ slab is 0.333 ft thick, a 6″ slab is 0.5 ft.

    Footing

    Total run × width × depth. Measure the run along the centerline of the trench and the corners take care of themselves.

    Round pier

    π × radius² × height, multiplied by the number of piers. Tube forms are sized by inside diameter, so a 12″ tube is 12″ of concrete.

    Stairs

    Each step is treated as a slab sitting on the one below it, so step n carries n × rise of depth. Solid stairs poured on grade, no void underneath.

    Bag yields

    BagYieldBags per yard
    40 lb0.30 ft³90
    50 lb0.375 ft³72
    60 lb0.45 ft³60
    80 lb0.60 ft³45

    Yields are for standard sand-mix and high-early bagged concrete. Fast-setting and countertop mixes run different, so check the bag.

    Bags or ready-mix

    Half a yard is the practical ceiling for bags — that is roughly 23 eighty-pound bags, or most of a morning. Past a yard, a short load is cheaper than the labor even after the short-load fee, and you get a consistent mix instead of 45 separate ones.

    Suppliers sell in quarter-yard increments and charge a short-load fee under 3 to 4 yards, so it is worth checking whether rounding up to the fee threshold costs less than paying it.

    Questions

    How many 80 lb bags are in a yard of concrete?

    Forty-five. An 80 lb bag yields about 0.60 ft³ and a yard is 27 ft³.

    How much waste should I add?

    Ten percent covers spillage and normal subgrade variation. Go to fifteen on rough or hand-dug subgrade where the bottom is uneven. Five is enough on formed work over compacted gravel.

    Why is my slab taking more than the calculator says?

    Almost always subgrade. An extra half inch of depth across a 20×20 slab is a third of a yard on its own. Screed the base before you order.

    Quantity takeoff only. These figures estimate how much material to buy. They are not structural design and say nothing about thickness, reinforcement adequacy, bearing capacity or footing depth for your soil and frost line. Check local code and use an engineer for structural work.